Shoring System: Temporary Soil Nailing
Client: TC Northwest Development, Inc.
General Contractor: Howard S. Wright
Shoring Contractor: Malcolm Drilling Company, Inc
Shoring Face Area: 96,500 Square Feet
Wall Depth Range: 80 to 96 feet
Status: Completed 2022
The muti-story office tower included 8-9 levels of underground parking with excavation depths extending to 96 feet. Soil conditions consisted of limited depths of fill over glacially overridden till and Advance Outwash sands and gravels, with limited exposures of hard silts near the base of the excavation. Conventional soil nail shoring was used, with limited depth vertical elements as required in specific areas to address underground utilities and potentially unstable fill. Up to 17 rows of nails were installed and maximum deformations of the shoring wall did not exceed 1 inch. This is deepest vertical soil nail wall in the world in an urban environment.
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.